publicly announcedAs of 2025-07-15Lifecycle status is not a quality score.
Developer
Blackstone
Operator
QTS
Place
Multiple proposed locations, Pennsylvania
Utility
Project-specific
Grid context
PJM
Investment
$25B+ announced
Power demand
Not consolidated here
Construction jobs
6,000+ created or supported annually, sponsor-modeled
Operating jobs
3,000+ created or supported, sponsor-modeled
Cooling approach
Not consolidated here
Quantified water
Not disclosed
Community benefits
Project-specific
Tax incentives
Project-specific
Reporting
GRID obligations may apply to covered permits
What changed
1 meaningful update
Only changes that materially affect BrooksFlow's current understanding appear here.
Pennsylvania changed its data-center permitting framework
Executive Order 2026-05 created the GRID framework for certain covered projects seeking Commonwealth permits, including local approval, disclosure, and enforceable commitments.
An earlier estimate and a later estimate may describe different project scopes, stages, or speakers. The timeline does not silently overwrite either.
2025-07-15publicly announced
Sponsor announced investment and broader economic-impact estimates.
2026-08-18expanded or revised
Covered future permits face GRID requirements.
What we do not know
Missing is not zero.
Direct payroll headcount
Project-by-project status
Water and utility terms
What kind of number is this?
Open every project claim.
Claims retain sponsor relationship, time status, geography, assumptions, and limitations.
Sponsor-reported
Blackstone/QTS announced more than $25 billion in investment, more than 6,000 jobs created or supported annually during construction, and more than 3,000 created or supported during operations.